Timeline

Q12015

Site Preparation Works

Highways
Funded by Enterprise Zone Funding - already fully approved (by both the Local Enterprise Partnership and Birmingham City Council)

Construction Start: Q1 2015

Completion: Q3 2016

Structure: Demolition and construct foundations and podium - South Funded by Enterprise Zone Funding - already fully approved (by both the Local Enterprise Partnership and Birmingham City Council)

Construction Start: Q3 2015

Completion: Q4 2017

Q32015

One Chamberlain Square

Construction Start: Q2 2016

Completion: Q4 2018

Q32016

Two Chamberlain Square

Construction Start: Q3 2016

Completion: Q1 2019

Q32018

One Centenary Way - Phase 2

Construction Start: Q3 2018

Completion: Q2 2021

Q32018

HOTEL - Phase 2

Construction Start: Q3 2018

Completion: Q1 2021

Q12019

Site Preparation Works

Structure: Demolition and construct foundations and podium - North

Construction Start: Q1 2019

Completion: Q4 2019

Q32019

Three Chamberlain Square - Phase 2

Construction Start: Q3 2019

Completion: Q2 2021

Q32020

Two Centenary Way - Phase 3

Construction Start: Q3 2020

Completion: Q1 2022

Q32021

One Congreve Square - Phase 3

Construction Start: Q3 2021

Completion: Q1 2023

Q32024

Three Congreve Square - Phase 3

Construction Start: Q3 2024

Completion: Q2 2026

Q42024

Two Congreve Square - Phase 3

Construction Start: Q4 2024

Completion: Q2 2026

Q12025

Pavilion, Centenary Way - Phase 3

Construction Start: Q1 2025

Completion: Q2 2025

Keep up to date on
progress at Paradise

If you would like to receive our project updates by email please register your details below.

The information supplied will be used for the Paradise development only. The information will be kept confidential and not passed to third parties.